Skip to main content

ADMINISTRATIVE LOSS

ADMINISTRATIVE LOSS
What is an administrative loss?

Widely accepted fact is that losses is just those technical and non-technical ones. However, some electric utilities shall we say electric cooperatives that includes Administrative loss.


The Administrative Loss is the component of Distribution System Losses that accounts for the electric Energy used by the Distribution Utility in the proper operation of the Distribution System. This shall include the electric Energy consumption of connected essential electrical loads in the following facilities, subject to the approval by the country's regulatory commission.

Distribution Substations;
  • Offices of the Distribution Utility;
  • Warehouses and Workshops of the Distribution Utility;
  • Other essential electrical loads of the Distribution Utility.
  • Administrative losses is simply the energy consumption of any infrastructure, substations, or anything that is deemed necessary for the operation of the utility.

Administrative Loss
Administrative Loss shall be the sum of the actual (i.e., metered) electric Energy consumption of the essential loads used by the facilities of the Distribution Utility during the billing period.
In equation form, the Administrative Loss shall be calculated as follows:
Administrative Loss =
= sum[Energy Consumed by Distribution Substations]
+ sum[Energy Consumed by Offices of the Distribution Utility]
+ sum[Energy Consumed by Warehouses and Workshops of the DU]

Calculation of Distribution System Losses
Calculation Period

Distribution System Losses shall be calculated monthly and shall coincide with the billing cycle adopted by the Distribution Utility. The Distribution Utility shall report the total number of days, number of hours and the inclusive dates covered by the billing cycle used as the Period for calculating the Distribution System Losses.


Total Distribution System Losses

Total Distribution System Losses

Σ[Energy delivered by the Transmission System] 
Σ[Energy delivered by Embedded Generating Plants] 
Σ[Energy delivered by Other Distribution Systems] 
Σ[Energy delivered by User Systems with Generating Units] 
Σ[Energy delivered to the Users of the Distribution System] 


The Total Distribution System Losses shall be computed as the net of all electric Energy input (i.e., electric Energy delivered to the Distribution System by the Transmission System, Embedded Generating Plants, other Distribution Systems, and User Systems with generating facilities) and of all electric Energy output (i.e., electric Energy delivered to the Users of the Distribution System) for the billing period. In equation form, the Total distribution System Losses shall be computed as follows: 
 

Comments

Popular posts from this blog

PARTS OF A POWER TRANSFORMER

What are the name of the basic parts of a Power Transformer? We can not deny the fact that only a handful of electrical engineering students are presently familiar with power transformers especially on what it looks like. Unlike a transformer we found in our homes, a power transformer’s appearance and construction is somewhat more complicated. It is not just a simple winding with a primary and secondary terminal although basically any transformer has one. The function that a power transformer plays in an electrical system is very important that an electric utility can not afford to loss it during its operation. Our discussion here will focus more on the basic parts and functions of a power transformer that are usually tangible whenever you go to a substation . Although not all power transformers are identical, nonetheless they all have the following listed parts in which the way of construction may differ.

ELECTRIC MOTOR FRAME SIZE STANDARD SPECIFICATIONS

ELECTRIC MOTOR FRAME SIZE STANDARD SPECIFICATIONS How is electric motor frame size being specified? Motor frame dimensions have been standardized with a uniform frame size numbering system. This system was developed by NEMA and specific frame sizes have been assigned to standard motor ratings based on enclosure, horsepower and speed. The current standardized frames for integral horsepower induction motors ranges from 143T to 445T. These standards cover most motors in the range of one through two hundred horsepower. Typical example of where you can locate the frame is shown in Fig 1.2.D – Frame No. The numbers used to designate frame sizes have specific meanings based on the physical size of the motor. Some digits are related to the motor shaft height and the remaining digit or digits relate to the length of the motor. The rerate, or frame size reduction programs were brought about by advancements in motor technology relating mainly to higher temperature ratings of insulating mate

ELECTRIC MOTOR NAMEPLATE SPECIFICATIONS

How do we interpret an electric motor nameplate? Motor standards are established on a country by country basis.Fortunately though, the standards can be grouped into two major categories: NEMA and IEC (and its derivatives). In North America, the National Electric Manufacturers Association (NEMA) sets motor standards, including what should go on the nameplate (NEMA Standard MG 1-10.40 "Nameplate Marking for Medium Single-Phase and Polyphase Induction Motors").